7:47am- Sawing asphalt on Pine Street next to post office for driveway approach
8:15am- Sidewalk removal at the corner of Washington and Pine Street heading West on Pine
8:51am- Applying base and compacting for the thickened curb, along side of the post office
11:03am- Installing 12" drain pipe under driveway on Pine Street
12:51pm- Excavating for more sidewalk, heading West on Pine Street.
2:11pm- First pour of the day 6+47.25 driveway approach
2:31pm- Final pour for the day, half of the drive approach and sidewalk just South of Post Office.