GC PAVING

 
7:50am- Saw cutting concrete 
 
9:10am- Building and setting forms for curb and gutter West of Washington on McCabe.
 
9:36 am- Excavating for more curb and gutter
 
1:09pm- first pour of the day. Had issues with air on first truck load. Added air which brought load in compliance.
 
 
2:26pm- Concrete ramp poured for school parking access in between Madison and Washington.
 3:56pm- Blankets set over curb and gutter for heating purposes. 
4:00pm- concrete curb and gutter sprayed for curing purposes
 