8:27am- Excavating for a driveway pour
9:34am- Building a structure for school sign relocation into the parking lot.
10:19am- Excavating on Pine, just West of the Post Office.
1:26pm- Concrete curb poured at the Cogdill sign in order to move sign into parking lot. Poured two approaches
1 @ 222 McCabe, West approach
2 @ the old VFW
2:28pm- Installing concrete pipe on the West end of Pine street.
3:27pm- Trenches dug for water run off and forms in place ready for sidewalk pour, just West of the post office on Pine Street